Archives
Categories

Contradictions and Non-Answers, Part 2: NJTA Responds to Turnpike Widening Comments

The New Jersey Turnpike Authority (NJTA) has posted official responses to public comments made on the NJ Turnpike expansion project, which would complete the dual-dual configuration (two 3-lane roadways in each direction) by adding up to 3 lanes in each direction between exits 6 and 9, an addition of 170 lane miles. Not surprisingly, the response document offers vague platitudes, ignores new data, and continues to refuse any solution to congestion that doesn’t include more pavement – making it the perfect companion piece to the original Environmental Impact Statement (EIS).

Tri-State has challenged several aspects of the project’s EIS, which found there would be no significant environmental impact (see MTR # 565). Most unconvincing is the NJTA’s evidence that the project is necessary as proposed and that it will provide sustainable congestion relief. Critically, the Authority ignores and fails to analyze whether additional lanes will fill with traffic due to induced demand and contribute to sprawl development (which leads to more congestion, and so on). These have been the historic consequences of highway construction and widening throughout the U.S.

The NJTA response document can be found here. Some notable passages are summarized below:

Purpose and Need

At the heart of any large project is a demonstrable purpose and need. According to the EIS, the purpose and need for the Turnpike widening is “to service existing and future travel demand.” The project assumes annual traffic growth of 2.4% northbound and 3.4% southbound between 2005 and 2032. Yet data we obtained from the Authority show that, since 2004, traffic volumes have leveled off in the project area, calling into question the project’s premise.

In response to a comment from a private citizen that the traffic data, based largely on numbers from 2005-2006, was stale and did not account for the effects of gas prices and the collapse of the housing market, the NJTA defends the timeliness of its data. It’s true that many large projects use numbers that are further out of date (see the Garden State Parkway widening). However, NJTA goes on to state “there is no strong evidence that these numbers have significantly changed over the last two years due to the economic issues stated in the comment.” This is simply false.

Alternatives to Widening

Large project proposals also require analysis of reasonable alternatives. In response to Tri-State’s comment that the Authority’s alternatives analysis was cursory and sometimes provided no analysis at all, the NJTA issued a blanket denial, stating that “alternatives were considered seriously in the EIS. … Sufficient analysis was included in the EIS to conclude that the alternatives are either not practicable from a feasiblility standpoint or would not reduce the needed additions in lane capacity to meet demand, safety, and operations requirements.” Here is the EIS’s treatment of ridesharing as an alternative in its entirety, which clearly lacks any analysis:

Ridesharing refers to strategies that encourage carpooling and vanpooling. Carpooling refers to the arrangement of a group of commuters that rideshare in a participant’s vehicle. Vanpools are generally similar to a carpool; however, instead of using a participant’s automobile, the group uses a van that can be supplied by employers, non-profit transportation advocacy groups or government agencies, with operating costs typically divided among group members and sometimes subsidized by the state and federal government. Depending upon the type of vehicles used, the capacity of a vanpool can be higher than a carpool. Carpools and vanpools tend to be most effective when they run on pre-determined fixed schedules and the number of occupied vehicle seats is maximized.

Environmental Impacts: Traffic, Sprawl, Greenhouse Gases

NJTA sometimes acknowledges induced demand, such as when it forecasts, without proof, less congestion on parallel roads because drivers will flock to the open road of the imagined Turnpike (see comments 3.15, 3.18, 3.61, 13.1, and 13.2). The agency also rejects non-stop cashless tolling because of induced demand, saying “additional traffic would be attracted to the turnpike as travel times for those users would be reduced.” If reduced travel time is undesirable, one has to wonder what the Authority is trying to achieve by widening the Turnpike.

But when it comes to the possibility that a widened Turnpike could lead to sprawl development and increased traffic, NJTA flatly denies the existence of induced demand. Many comments, including Tri-State’s, criticized the flimsy study of secondary impacts like the sprawling development associated with big capacity adding projects like this one — the EIS analyzes land use impacts only within a mile of the corridor (comment 2.6). As its only defense, NJTA says it has done all that is required of it according to Executive Order 215 – the document that requires agencies to prepare an EIS for large projects – and that there is further study of secondary impacts in the applications for Dept. of Environmental Protection Land Use Permits required by state law. This lack of study does not stop NJTA from saying that “a widened Turnpike would not exacerbate long term traffic congestion in Central New Jersey” (comment 2.5) and that no sprawl will be induced (comment 3.52).

In 2007, Gov. Corzine signed Executive Order 54, which calls for the reduction of NJ’s carbon footprint by twenty percent. We commented that the widening of the Turnpike would undermine this and other state environmental goals by encouraging sprawl and increasing traffic volumes. In response, the NJTA denies the allegation and offers the DEP’s concurrence in the finding of no significant adverse impact documented in the EIS. With no evidence or data backing either agency’s claim, the stamp of approval amounts to little more than “because we said so.”

Due Diligence Needed For a $2.7B Project

According to some news reports, the estimated cost of the Turnpike widening has risen to $2.7 billion. According to the Authority’s own projections, by 2032 travel times on the widened Turnpike will be higher than they are today (see, for example, comment 3.60). Before the NJTA embarks on a project that will cost almost $3 billion and fail to provide sustainable congestion relief, it owes New Jerseyans a thorough study of the alternatives, and public responses that make sense.

Share This Post on Social
Subscribe
Notify of
guest

8 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Glenn
Glenn
15 years ago

Never mind the whole induced demand argument, the NJ Tpk needs **at minimum** one additional lane in each direction between Exits 6 & 9. Period. This is fact (you do not require engineering studies to prove this, just get caught in a 11PM traffic jam on a holiday weekend!), and it needs to be completed yesterday. Anyone who disputes this is simply in denial, as there is a chronic & severe bottleneck in this corridor.

Now, additional lanes beyond that? Well, we could argue the “facts” (notice the quotes)on projected volumes endlessly.

Volumes may be leveling-off (or even slightly dropping), but we all know that’s due to the substantial increase in fuel costs.

I’m all for multi-modal transportation solutions, but do to pre-existing conditions or just plain neglect by the “powers that be”, there are just some instances where we have no choice, and this is a perfect example.

Noon
15 years ago

Thanks! Really amazing. Big ups!

J
J
15 years ago

If the facts are so flimsy, the logic so contradictory, and the process so clearly not in accordance with the law, why not sue the state? It was done for Atlantic Yards. If TSTC has a legal team, it should be moving ahead with this. If not, there should be some movement to set one up. This type of process has been rubber stamped for years. If the law says they must analyze alternatives, then someone has to sue to uphold the law.

Douglas Willinger
15 years ago

True.

It may do the same for I-95 through Philadelphia. Hopefully the planning there, such as the hopefully to-be-undergrounded segment will acknowledge that.

Edward
Edward
15 years ago

The connnection between I-95 and Pennsylvania Turnpike in Southeastern Pennsylvania in under construction. I-95 will be routed onto the PA and NJ Turnpikes and a new bridge over the Delaware River will be constructed. This will bring large amounts of traffic onto the NJ Turnpike. That alone will require NJ Turnpike to be widened.

Erik Engquist
Erik Engquist
15 years ago

If one project to increase road capacity “requires” connecting roads to increase their capacity, it would produce an endless chain of road-widening projects. If not, then something must be wrong with the logic of posts 1 and 2.

trackback

[…] State Parkway widening projects, opting to simply lay more pavement (see, for example, “Contradictions and Non-Answers Part 2,” July ‘08; MTR # […]

trackback

[…] promise is another sorry chapter in the history of the Turnpike widening project, which has been poorly justified and promises little but induced traffic and more sprawl.  The trees would have offered noise and […]

8
0
Would love your thoughts, please comment.x
()
x