The Tappan Zee/Interstate 287 study team’s decision to split the project’s environmental review into multiple phases — first selecting a transit alternative and finalizing bridge design, then finalizing the details of the transit system while the bridge is constructed, and finally building transit after completion of the bridge — is predicated on reasons which seem sound. The phasing will allow bridge construction to occur while NYSDOT goes through the time-consuming work of cooperatively developing a transit system that fits into local communities. Speeding up construction could also save money at a time when the cost of construction materials is far outpacing inflation. That being said, the announcement has reminded many advocates of the George Washington Bridge, which was designed to accommodate a transit system which was never built.
Begun in 1926 and completed in the fall of 1931, the George Washington Bridge was conceptualized by the Port Authority and designed by O.H. Ammann, who would go on to design five other bridges in New York City, including the Triborough and Verrazano. In a concession both to geological and political considerations, the bridge was located at considerable distance from work and population centers to the south, such as Hoboken. This location dictated that the bridge would first serve automobile traffic.
The bridge was financed by a $60 million bond issuance, and there was considerable pressure to begin collecting toll revenue as soon as possible. Because of this, the bridge was to be built in stages. In an article published in the Transactions of the American Society of Civil Engineers in 1933, the project engineers wrote that the bridge “is designed to carry a 90 ft roadway flanked by two 10 ft sidewalks on the upper deck and 4 electric rail tracks on a lower deck. Only the upper deck has been built to date (1932) and the center portion is unpaved…”
The rationales for constructing the GW Bridge in phases included speed and cost, echoing those of the Tappan Zee project team. As Ammann wrote in Transactions, “A controlling aim in the development of the design has been to permit the later enlargement… of the bridge and its approaches… such an arrangement is of deciding economic advantage. It permits the opening of the bridge to traffic years in advance of the final completion, [and] effects a large saving in initial cost and interest during construction and after completion [emphasis added].”
Ammann was aware of the emerging primacy of car traffic but felt that “the more efficient and economical transportation of people by electric rail service will become a necessity.” These plans never came to fruition as auto-centric planning came to dominate NYC. By the time Robert Moses commissioned a study to add a new deck to the bridge in 1955, it was to consider the addition of lanes serving car traffic, not “electric rail” as originally anticipated.
It is easy to overstate the similarities between the GW and Tappan Zee projects. Though the GW Bridge was designed to accommodate transit, the transit system itself was not part of the project. By contrast, the Tappan Zee study included plans for I-287 corridor transit from its inception, and the agencies working on the project have invested years in studying and refining transit plans. Furthermore, there is strong sentiment among Hudson Valley policymakers that the I-287 corridor needs transit. Nevertheless, the George Washington Bridge stands as an example of transit intentions gone awry.
The Tappan Zee project team has announced that it will hold open houses on changes to the study, including additional transit alternatives and new alternatives combining transit with a rehabilitated bridge, on February 26, 27, and 28 in Purchase, Goshen, and West Nyack, respectively (details here).
Image: The George Washington Bridge in its original, single-deck configuration. (Encyclopedia Britannica)
Paul Murphy is the Tri-State Transportation Campaign’s intern.
Thanks for this, Paul! In order to make up for the disaster of the George Washington and Tappan Zee Bridges’ transit-less designs (and the subsequent sprawlification of Bergen, Orange and Rockland Counties), I think they should build the transit portion first, and then add the roadways later … if they have the money.
Or maybe they could put trains on the GWB after all.
The likelihood of commuter rail on the TZ bridge is more remote than it ever was on the GW for the following reasons: (1)Funds are extremely limited due to the economy, our deficit, the war and other projects that have a much greater ridership potential, ie. the Second Ave. subway and the LIRR connection to the East Side. (2)According to the DOT’s consulting engineers, in order to have a commuter rail in the 87/287 corridor, tunnels are needed to level the terrain to allow trains to negotiate the various elevations. About 20 miles between Rockland & Westchester. Costs have not yet been estimated for this. Yet the State agencies have rejected any tunnel crossing under the Hudson that could accommodate rail, bus and possibly trucks. Removing these elements could add many years to the life of the bridge. Our fear has always been that they will build a bridge large enough to have rail, but that it would not happen, leaving us with lanes for additional traffic in this overburdened area. The separation of the bridge cconstruction and the transit positions the DOT to do exactly this.
George Sherman
President, Rockland Branch
Concerned Citizens for Resonsible Development(CCRD)
845-358-8364
[…] into separate phases was surprising enough (MTR ran stories on the announcement of the split and on an ominous precedent). But a scoping update document (PDF), made public by the study team last week, contains additional […]
New tunnel drilling technologies should make adding a hi speed rail component to the I-287 corridor more not less feasible.
However, the western portion would be best routed via the Route 119 corridor which could accommodate new TOD.
And then, increase the diameter of the proposed Cross Sound Link tunnel from 55″ to 60″ bore to allow a lower deck to accommodate a 2 track extension, continuing along the Route 135/future LI I-287 corridor to the Sunrise Highway/future I-287/I-78 corridor, with a spur to the beach.
Alas, so many are conditioned to think of things as rail versus highway rather than infrastructure versus the pentagon-pentagram!